For qualifying housing building permits, AB 1621 limits the reviews an agency may require or request to two, starting January 1, 2027. But it does not guarantee a faster permit or eliminate a third review: after two reviews, an applicant may request another submission if the application remains noncompliant. San Francisco data shows that housing permits in the measured period were, at the median, approved on the third round of review. The practical change is who must choose to continue, and when.
For owners, developers, project managers, architects, and contractors working through plan check, the important distinction is that the two-review cap counts plan check and specification reviews, not the completeness exchange that comes before them. And AB 1621 also sets a limit on when an inspector can require field changes that diverge from approved plans. Read the law as a rule for sequencing decisions, not as a speed guarantee.
What the two-review cap actually changes
AB 1621, Chapter 780 of the Statutes of 2026, amends California Government Code section 65913.3. With no urgency clause, it takes effect January 1, 2027, under the ordinary effective-date rule for non-urgency statutes enacted in 2026. The statute says an agency may not require or request more than two plan check and specification reviews in connection with a building permit application for the specified housing development projects. It also says an agency may deny an application that does not meet permit standards after two reviews. If the application remains noncompliant, the applicant may request additional submittals. [1]
In practical terms, an agency can require two reviews, but a third submission becomes the applicant’s request, not another round the agency can demand under this provision. That makes the decision at review two more consequential. Treating it as a placeholder can leave the owner facing an early denial decision or needing to choose whether to pursue another submission and extend the project’s calendar.
A “round” also needs to be understood in context. The two-review cap counts plan check and specification reviews only. The completeness exchange happens before that under subdivision (b) and is not counted toward the two. So “two reviews” should not be read as two total exchanges with the agency. Completeness exchanges therefore do not, by themselves, use up the two-review cap. The exact next step depends on what the review says and how the applicant chooses to respond. [1]

Completeness remains a separate gate
The two-review cap applies within the review of a complete application. The completeness determination happens earlier, under a different part of the statute. For covered housing applications, the agency has 15 business days after receipt to determine completeness, and its list of missing items is limited to items on its published checklist. If it misses that deadline, and the application or resubmission states that it is for a postentitlement phase permit, the application is deemed complete. AB 1621 does not cap the number of completeness exchanges before plan check begins. [1]
That distinction matters. A project team may be working through missing application materials before any substantive plan review is counted. An owner should not treat “two plan check reviews” as “two total exchanges with the agency” or assume the cap shortens the completeness stage.
San Francisco’s Permit Center describes completeness, first plan review, and revision review as separate steps. The City also says its building permit review dashboards include in-house permits, typically the more complex permits, and that a small percentage of applications have state-mandated timelines. Its published performance targets are not a guarantee for an individual application. [4]
Before submitting, compare the package to the responsible agency’s published checklist. Assign an owner for each drawing, specification, calculation, and supporting document. Keep a dated submittal register that records what was sent, what the agency identified as incomplete, and when each response was returned. This does not guarantee completeness, but it gives the team a clearer record of which stage it is in.

San Francisco’s third-submission pattern is the reason to plan ahead
San Francisco’s data makes the policy change concrete. The Budget and Legislative Analyst’s March 2026 report found that housing building permits issued from January 1, 2024, through August 12, 2025, had a median of three review rounds. The reported measure included permits filed any time before August 12, 2025, and the report notes that some earlier filings included entitlement time. The median permit in that group was approved on its third submission. [2]
The same report puts time against those rounds. Permits for projects adding housing units that were filed before August 12, 2025 and issued between January 1, 2024 and August 12, 2025 had a median of 280 days from filing to issuance. For permits both filed and issued between January 1, 2024 and August 12, 2025, a narrower group that excludes entitlement time, the median was 114 days. The median number of days applications spent with each reviewing department, for housing permits filed and issued in 2024 and through August 2025, was 30 with the Department of Building Inspection, 24 with Planning, and 14 each with Public Works, the Public Utilities Commission, and the Fire Department. [2]
The tail is longer than the median suggests. In a separate dataset of 1,371 in-house permits filed and issued between January 1, 2024 and September 15, 2025, 213 applications, or 16 percent, took five or more rounds of review before issuance, 19 took ten or more, and four took seventeen, the maximum in the data. [2]
That is a useful warning, not a 2027 forecast. The dataset covers a past period and should not be treated as a prediction for a specific project or as a postentitlement-only schedule. The report also notes an important data limitation: the city did not track total elapsed time for each review cycle or divide that time between the city and the applicant. [2]
San Francisco already had an administrative response to repeated review. In a September 2025 customer bulletin, the Department of Building Inspection said rechecks exceeding three rounds of review comments were subject to supervisor escalation, and that the escalation approach had been expanded citywide to include completeness review and plan check. That is an escalation policy, not the same thing as the statutory two-review cap. [3]
For project teams, the operational lesson is to start organizing the response well before the second review closes. Consolidate comments across disciplines, identify decisions that depend on one another, and make the responsible professional clear for each response. If a comment could change scope, cost, procurement, or sequencing, bring that consequence into the decision early instead of leaving it for a later cycle.
The cap’s scope and start date need careful reading
The two-review provisions are written for housing development projects in two unit groupings: 25 units or fewer, and 26 units or more. They concern reviews connected with an application for a building permit. The same subdivision says the cap does not change the number of submissions an agency may require for a postentitlement permit other than a building permit. Grading, demolition, and offsite improvement permits should not be assumed to have the same two-review limit. [1]
The statute’s definition of “postentitlement phase permit” also reaches beyond building permits, including interdepartmental reviews required for building permit issuance, such as plan checking and building inspection. But the cap itself is written within paragraphs addressing housing development projects. How far it reaches outside housing is a question to take to the responsible agency and a qualified professional, rather than assume from the broader definition. The law says the applicable amendments extend to all cities, including charter cities. [1]
The text reviewed does not address how the new cap applies to applications already in plan check on January 1, 2027. If your project may straddle that date, ask the agency for its position in writing and consult a qualified professional. Do not assume the new rule automatically applies to, or excludes, a pending application.
AB 1621 also changes appeal timing under this section: final written determinations are due within 30 business days for projects of 25 units or fewer and 45 business days for projects of 26 units or more, down from 60 and 90 business days. It also provides for a writ of mandate in specified circumstances, including a denied appeal or no decision within the applicable timeline. These appeal changes are separate from the plan check count. [1]
The inspection provision affects field decisions too
Once plans are approved, AB 1621 says an agency may not require or request an action or inaction resulting from a building inspection that would deviate from the previously approved building plan or similar approval, unless the request is accompanied by written findings based on substantial evidence. The findings must establish one of two things: a reasonable person could not interpret the approved plan as compliant with applicable standards, or the deviation is necessary to address a specific adverse impact on public health or safety. [1]
This does not remove inspections or excuse compliance with permit standards. It changes the framework for requiring a field deviation from an approved plan. For an owner and project team, a field condition that prompts a proposed change should be documented and routed deliberately, not handled only through an informal verbal direction.

As a practical recordkeeping step, preserve the approved plan set, note the specific field condition, and record who raised the issue and what written direction or findings support any required deviation. The project team can then route the technical response to the appropriate design and construction professionals and assess any change-order or sequencing implications. The statute’s separate clarification that plan checking and building inspection are included in interdepartmental reviews is declared to reflect existing law, not to create a new obligation. [1]
The two decisions to make before January 1
Before January 1, 2027, document the current plan check round count for each active building permit application. Keep the agency’s comments and the project’s responses together so the team can distinguish completeness exchanges from substantive plan reviews.
Then build a possible third round into the schedule as applicant-controlled time. After two reviews, the decision to request another submittal may belong to the applicant. It is not a promise that the city will require a third round, and it is not a promise that the permit will be issued faster.
For owners coordinating design, construction, and development decisions, Atlas Premier’s construction services and development services describe relevant service areas.
Ready to move your project from concept to completion?
Contact Atlas Premier Services & Consultants today.
Atlas Premier Services & Consultants
Strategic Solutions. Trusted Execution.
Lake Merritt Plaza
1999 Harrison Street, 18th Floor
Oakland, CA 94612
Phone: (888) 999-8417
Email: admin@atlas-premier.com
Website: www.atlas-premier.com
Sources
- California Legislature, AB 1621 (Wilson), Chapter 780, Statutes of 2026, chaptered bill text and status page. Approved and filed September 29, 2026. Bill text; bill status. Accessed November 14, 2026.
- San Francisco Budget and Legislative Analyst, “Post-Entitlement Permitting in San Francisco,” Policy Analysis Report to Supervisor Bilal Mahmood, March 5, 2026. https://harveyrose.com/wp-content/uploads/2026/03/BLA.Post-Entitlement-Permitting.030526.pdf. Accessed November 14, 2026.
- San Francisco Department of Building Inspection, “New Solar Permit, Cancelling Abandoned OTC Applications, Recheck Escalation, Reference Drawings and New Fee Rates,” September 2, 2025. https://www.sf.gov/new-solar-permit-cancelling-abandoned-otc-applications-recheck-escalation-reference-drawings-and-new-fee-rates. Accessed November 14, 2026.
- City and County of San Francisco, Permit Center, “Permit performance metrics.” https://www.sf.gov/permit-performance-metrics. Accessed November 14, 2026.
Disclaimer: This content is for general informational purposes only and does not constitute legal, financial, engineering, construction, regulatory, or other professional advice. Reading this content does not create a client or contractual relationship with Atlas Premier Services & Consultants. Because every project and property is different, consult qualified professionals regarding your specific circumstances. Atlas Premier Services & Consultants makes no warranties regarding the accuracy or completeness of this information and is not responsible for third-party content or references. Testimonials, examples, and case studies are illustrative only and do not guarantee similar results.