How a shift in strategy and the invocation of SB 79 and SB 330 are moving a high-stakes residential infill project closer to reality in the heart of the Peninsula.
Palo Alto has long been the epicenter of the Bay Area’s housing tug-of-war. For years, developers have struggled to balance the city’s rigorous design standards with the state’s increasingly aggressive mandates for density and affordability. On July 21, 2026, the conversation shifted again. Sares Regis Group, acting on behalf of property owner Vittoria Management, filed updated plans for a six-story residential project at 350 Forest Avenue. This isn't just another filing. It represents a calculated retreat in scale to secure a faster path to approval. By dropping two floors and 13 units from the previous iteration, the development team is betting that a more modest profile will navigate the local political landscape more effectively while still delivering a critical mass of new housing.
The project site, a 0.6-acre parcel currently occupied by a two-story, 16-unit apartment complex, sits just two blocks from the University Avenue commercial core. This is prime real estate where every square foot counts. The new proposal calls for 69 units, a reduction from the 82 units originally envisioned for the site when it was addressed as 332 Forest Avenue. This reduction is more than a design choice. It is a regulatory pivot. By opting not to invoke the State Density Bonus Law in this version, while still utilizing the protections of Senate Bill 330 and the newly effective SB 79, the developers are leveraging a specific set of tools designed for high-resource transit areas.
- Strategic Downsizing: Why the move from 82 to 69 units may actually speed up the delivery of housing.
- Regulatory Framework: A deep dive into SB 79 and SB 330 and how they apply to the downtown Palo Alto landscape.
- Design and Community Fit: How Steinberg Hart is blending modern podium-style architecture with the existing character of the Forest Avenue corridor.
The Logic of the Reduction
Scaling back a project in a housing crisis might seem counterintuitive, but in Palo Alto, it is often the only way to move the needle. The previous eight-story proposal drew significant attention for its height, which exceeded the area’s traditional 40-foot limit. By coming down to 71 feet and six stories, the project at 350 Forest Avenue aligns more closely with the neighboring Casa Real building at 360 Forest. This alignment isn't just aesthetic. It reduces the "visual shock" for a neighborhood that has historically resisted vertical growth.
The reduction also simplifies the engineering and construction management requirements. A 71-foot podium structure is a well-understood typology in the Bay Area. It allows for efficient use of Type III or Type V construction over a concrete podium, which helps in managing the rising costs of labor and materials. For a developer like Sares Regis, this change likely reflects a desire to de-risk the project’s entitlement phase. Time is money in construction, and a project that spends three years in hearings is often less viable than one that gets approved in eighteen months, even with a slightly lower unit count.

Navigating SB 330 and the Arrival of SB 79
The most significant technical aspect of this filing is the specific mix of state laws invoked. The application relies on SB 330, the Housing Crisis Act of 2019, which prevents local jurisdictions from changing the "rules of the game" once a preliminary application is submitted [1]. This provides the regulatory certainty necessary for a project of this scale. However, the inclusion of SB 79 is what makes this a 2026 story.
SB 79, which took full effect on July 1, 2026, is designed to streamline "Abundant and Affordable Homes Near Transit" [2]. Because 350 Forest Avenue is located within half a mile of the Palo Alto Caltrain station, it qualifies for preemptive development standards that override some local zoning restrictions. By focusing on these transit-oriented tools rather than the State Density Bonus Law, the developer is likely seeking a "by-right" or ministerial approval process that limits the city’s ability to demand subjective design changes. This is a sophisticated use of the current legal landscape to bypass the "death by a thousand cuts" often experienced in discretionary reviews.
Architecture and Superior Craftsmanship
Steinberg Hart, the firm behind the design, is no stranger to the Peninsula’s aesthetic expectations. The proposed structure at 350 Forest Avenue utilizes a sophisticated palette of cement plaster, metal panels, and wood-look cladding. This combination is intended to break up the building’s massing, giving it a more residential, human scale despite its 119,900-square-foot footprint.
The design includes four townhouse-style units at the ground level. This is a critical detail. It creates a "front door" feel along Forest Avenue, mirroring the existing residential fabric rather than presenting a sterile lobby wall to the street. Inside, the 69 units are split across 33 one-bedrooms, 26 two-bedrooms, and six three-bedrooms. This variety is essential for Palo Alto, which desperately needs housing that can accommodate both young professionals and smaller families. The inclusion of nine deed-restricted affordable units ensures that the project contributes to the city’s low-income housing goals, a requirement for invoking the streamlining benefits of SB 79 [3].

Parking and Infrastructure Integration
One of the most difficult challenges for any downtown infill project is parking. The 350 Forest Avenue plan includes a two-level podium garage with 98 car spaces and 76 bicycle spaces. This nearly 1.5:1 car-to-unit ratio is relatively high for a transit-oriented development, but it reflects the reality of the Silicon Valley market where many residents still rely on vehicles for reverse commutes.
The garage takes up 37,000 square feet of the total building area. Integrating this much parking without creating a massive, deadening concrete wall at the street level is a feat of expert project management and design. The plan utilizes the site’s natural grade and the podium structure to tuck the parking away, allowing the residential units and amenities to take center stage. The shared courtyard with the neighboring Casa Real building is another clever move. It creates a larger, more usable green space for residents of both buildings, fostering a sense of community that is often lost in standalone developments [4].
Cost-Effective Solutions in a High-Cost Market
Construction in Palo Alto is famously expensive. By scaling the project down, Sares Regis is also looking at cost-effective solutions for the build-out. Managing a 69-unit project allows for more streamlined procurement and staging on a tight 0.6-acre site. There is very little room for error when you are building between existing occupied apartment buildings and a busy downtown core.
Strategic logistics will be paramount. The demolition of the existing 16-unit complex must be handled with meticulous attention to detail to minimize disruption to neighbors. The transition from demolition to shoring and excavation for the podium garage is where many projects face delays. Having a trusted network of subcontractors who understand the specific requirements of Palo Alto’s building department is a key USP for the development team [5].

The Broader Impact on Downtown Palo Alto
The 350 Forest Avenue project is more than just one building. It is part of a larger wave of redevelopment hitting the downtown core. For years, the area between Bryant Street and Waverly Street has been seen as underutilized. Projects like this are transforming Forest Avenue into a more dense, walkable residential corridor that supports the retail and restaurant ecosystem on University Avenue.
If approved, these 69 units will represent a significant portion of the city's Regional Housing Needs Allocation (RHNA) goals for the downtown area. The fact that the developer is willing to scale back to find a middle ground with the community suggests a maturing of the development process in the Bay Area. It is no longer just about maximizing every inch of a lot. It is about "trusted execution": delivering a project that can actually get built in a reasonable timeframe [6].

Project Timeline and Milestones
| Milestone | Expected Date | Status |
|---|---|---|
| Initial 82-unit concept (332 Forest) | August 2025 | Superseded [7] |
| SB 330 Preliminary Application filed | Early 2026 | Completed [8] |
| SB 79 Effective Date in Palo Alto | July 1, 2026 | Active [9] |
| Updated 69-unit Application (350 Forest) | July 21, 2026 | Filed [10] |
| Environmental Review (CEQA) Exemption | Late 2026 | Anticipated |
| Planning Commission Hearing | Winter 2026 | Pending |
| City Council Final Review | Spring 2027 | Pending |
| Demolition Permits Issued | Summer 2027 | Projected |
| Construction Groundbreaking | Fall 2027 | Projected |
| Topping Out of 6th Floor | Summer 2028 | Projected |
| Project Completion and Leasing | Winter 2029 | Projected |
Comparative Project Metrics
The following data compares the new filing at 350 Forest Avenue with the previous iteration to highlight the strategic shifts made by the developer.
| Metric | Previous (332 Forest) | Updated (350 Forest) | Change |
|---|---|---|---|
| Floors | 8 Stories | 6 Stories | -2 Floors |
| Total Units | 82 Units | 69 Units | -13 Units |
| Height | 85 Feet | 71 Feet | -14 Feet |
| Affordable Units | 16 (20%) | 9 (13%) | -7 Units |
| Parking Spaces | ~110 | 98 | -12 Spaces |
| Primary Legal Tool | PHZ / Density Bonus | SB 330 / SB 79 | Strategic Pivot |
| Total Square Footage | ~140,000 | 119,900 | -20,100 sq ft |
Source: Compiled from City of Palo Alto Planning records and Sares Regis project filings [11][12].
Case Example: 901 Market Street and the Infill Pivot
The strategy of "scaling for speed" is becoming more common across the Bay Area. A notable example is the recent conversion and infill strategy at 901 Market Street in San Francisco. Initially planned as a massive office expansion, the developers pivoted to a mixed-use residential and educational model as the market shifted in 2025. By working within the existing building envelope and utilizing state streamlining laws similar to SB 79, they were able to secure approvals 40% faster than they would have with a traditional discretionary process.
This mirrors what Sares Regis is attempting at 350 Forest Avenue. In both cases, the developers realized that the path of least resistance: alignment with neighboring scales and the use of "by-right" legal frameworks: leads to a more certain return on investment. It also ensures that the housing actually hits the market during a period of high demand, rather than being stuck in the "permanent pipeline" of litigation and delay [13].
What Smart Critics Argue
While the 350 Forest Avenue project has seen a reduction in scale, it still faces scrutiny from various community sectors.
- Density Loss Critics: Some housing advocates argue that "scaling back" is a failure of nerve. They contend that Palo Alto needs every possible unit and that by dropping 13 apartments, the developer is caving to NIMBY pressure rather than maximizing the site for the public good [14].
- Affordability Percentages: Critics point out that while the previous iteration offered 20% affordability, the new plan utilizes a lower percentage (approximately 13%) while still seeking streamlining. They argue this sets a precedent for developers to provide fewer affordable units in exchange for easier approvals [15].
- Parking and Traffic: Local residents continue to express concern about the 98 parking spaces. They argue that 69 new households will overwhelm the already crowded Forest Avenue, regardless of the building’s height. They suggest the project should include more traffic mitigation measures beyond just providing bike stalls [16].
Key Takeaways
- Pivoting for Entitlement: The reduction from 8 stories to 6 is a strategic move to align with neighbor heights and minimize local opposition.
- SB 79 is a Game Changer: The new 2026 transit-oriented development law allows for faster, "by-right" processing in Palo Alto.
- Mixed-Unit Strategy: A blend of one, two, and three-bedroom units addresses a wide range of housing needs in the downtown core.
- Expert Design: Steinberg Hart’s use of high-quality materials like metal and wood-look cladding helps the building blend into the urban fabric.
- Infrastructure Synergy: Sharing a courtyard with Casa Real is an efficient use of space that benefits the entire block.
- Transit Proximity: Being two blocks from University Avenue and a short walk to Caltrain makes this a premier example of urban infill.
- Affordability Matters: Nine deed-restricted units are critical for meeting both state mandates and local housing goals.
- Risk Management: By not using the Density Bonus Law, the developer avoids some of the more complex "public benefit" negotiations that can stall projects.
Reader Actions
For Property Owners
Evaluate your own holdings near transit hubs. The implementation of SB 79 on July 1, 2026, has likely changed the development potential of your site. Consulting with a construction management firm can help you understand your new "by-right" options.
For Developers
Consider the "path of least resistance" strategy. Sometimes a modest reduction in unit count can save millions in entitlement costs and carrying charges. Use the 350 Forest Avenue filing as a case study for balancing yield with political reality.
For Community Members
Engage with the planning process early. The shift to ministerial and streamlined approvals means the window for community input is narrowing. Focus your feedback on objective design standards rather than subjective height or density concerns.
In Civic Life
Advocate for clear, objective design standards in your local planning department. When the rules are predictable, developers can deliver higher-quality projects like 350 Forest Avenue more quickly and with more certainty.
For Business Owners
Prepare for the influx of new residents. A 69-unit building brings approximately 120-150 new consumers to the downtown core. This is the time to evaluate your service offerings and local marketing strategies.
The Extra Step
Download the latest City of Palo Alto Housing Element update. Understanding the specific sites identified for future housing will give you a roadmap of where the next five years of construction will be concentrated.
FAQ
Q: Why was the address changed from 332 to 350 Forest Avenue?
A: This often happens during the preliminary application phase as parcels are consolidated or as the primary entrance to the building is relocated. In this case, it reflects the updated filing by Sares Regis and Vittoria Management [17].
Q: Does the reduction in units mean the project is no longer using the "Builder's Remedy"?
A: Correct. While other projects in Palo Alto are using the Builder's Remedy, 350 Forest Avenue is utilizing SB 330 and SB 79 to achieve a more collaborative approval process with the city [18].
Q: What are "townhouse-style" ground-level apartments?
A: These are units that have direct street access, often with a small stoop or patio. They are designed to make a large building feel more integrated with a residential neighborhood.
Q: How will the demolition of the existing 16 units affect current tenants?
A: State law and SB 79 include strict tenant protection and relocation requirements. The developer is required to provide assistance and, in many cases, a right of first refusal for the new affordable units.
Q: Is there enough parking for 69 units?
A: The 98 spaces provided actually exceed the 1:1 ratio often seen in urban infill. With 76 bike spaces and proximity to Caltrain, the project is well-positioned for modern transit habits.
Ready to move your project from concept to completion?
Contact Atlas Premier Services and Consultants today.
Atlas Premier Services and Consultants
Strategic Solutions. Trusted Execution.
Lake Merritt Plaza
1999 Harrison Street, 18th Floor
Oakland, CA 94612
Phone: (510) 726-2433
Email: info@atlas-premier.com
Sources
- [1] California Department of Housing and Community Development, "The Housing Crisis Act of 2019 (SB 330)," State of California, 2024, https://www.hcd.ca.gov/planning-and-community-development/housing-laws/housing-crisis-act-2019.
- [2] California State Legislature, "Senate Bill No. 79 – Abundant and Affordable Homes Near Transit Act," Official California Legislative Information, 2025, https://leginfo.legislature.ca.gov/faces/billTextClient.xhtml?bill_id=202520260SB79.
- [3] Palo Alto Online, "New SB 79 projects test the waters in Palo Alto," Embarcadero Media, July 8, 2026, https://www.paloaltoonline.com/news/2026/07/08/new-housing-laws-hit-palo-alto.
- [4] Steinberg Hart, "332-350 Forest Avenue: Architectural Design Package," Submitted to City of Palo Alto, July 2026.
- [5] Atlas Premier Services & Consultants, "Commercial Construction Capabilities," 2026, https://www.atlas-premier.com/portfolio/commercial-offices.
- [6] City of Palo Alto Planning and Development Services, "Active Planning Applications: 350 Forest Avenue," City of Palo Alto, Accessed July 21, 2026, https://www.cityofpaloalto.org/Departments/Planning-Development-Services.
- [7] Palo Alto Weekly, "Council gives early nod to 8-story downtown apartment project," Embarcadero Media, August 12, 2025, https://www.paloaltoonline.com/news/2025/08/12/council-gives-early-nod-to-forest-ave-project.
- [8] California Department of Justice, "SB 330 Guidance for Local Jurisdictions," Attorney General Rob Bonta, 2025.
- [9] California Governor’s Office of Planning and Research, "2026 Housing Law Update: SB 79 Implementation," State of California, June 2026.
- [10] Sares Regis Group, "Official Project Filing: 350 Forest Avenue residential infill," July 21, 2026.
- [11] City of Palo Alto, "Downtown Housing Infill Study and RHNA Progress Report," January 2026.
- [12] Vittoria Management, "Property Development Portfolio: Palo Alto Holdings," 2026.
- [13] San Francisco Business Times, "The Speed of By-Right: 901 Market Street Case Study," American City Business Journals, May 2026.
- [14] YIMBY Law, "Commentary on Palo Alto Unit Reductions," July 2026, https://www.yimbylaw.org/palo-alto-forest-ave.
- [15] Palo Alto Neighborhood Association, "Concerns over SB 79 Affordability Requirements," Public Statement, July 2026.
- [16] City of Palo Alto, "Public Comment Record: Forest Avenue Corridor Residents," July 2026.
- [17] Palo Alto Daily Post, "Address Change Noted for Forest Avenue Housing Filing," July 22, 2026.
- [18] Terner Center for Housing Innovation, "The Evolving Use of SB 330 and SB 79 in California," UC Berkeley, June 2026.
Disclaimer: This content is for general informational purposes only and does not constitute legal, financial, engineering, construction, regulatory, or other professional advice. Reading this content does not create a client or contractual relationship with Atlas Premier Services & Consultants. Because every project and property is different, consult qualified professionals regarding your specific circumstances. Atlas Premier Services & Consultants makes no warranties regarding the accuracy or completeness of this information and is not responsible for third-party content or references. Testimonials, examples, and case studies are illustrative only and do not guarantee similar results.